October, 2002 ~ Before work begins

 Tuesday 4/6/04 ~ Work begins


Friday 4/16/04 ~ The drainage stone is on site, all 100 tons+!!!!.

Thank you Weldon Materials

Saturday 4/17/04 ~ The excavation begins

Thank you A & N Landscaping & the D.P.W.

Tuesday 4/20/04 ~ Playground covered rain predicted

Saturday 4/24/04 ~ Putting down the stone. Thank you D.P.W.

All cleaned up

Thursday 4/29/04 ~ Marking the holes with Corby Associates of Ridgefield, NJ

Thursday 4/29/04 ~ Playground equipment delivered.

Thank you ABF Freight for donating the shipping

Friday 4/30/04 ~ Unloading the playground and digging the holes, Thank you D.P.W.

Friday ~ 4/30/04 ~ Sorting out the parts

Saturday 5/1/04 In the beginning

 

 